OpenLegislation

Paragraph 27 Onshore decommissioning

Original text. Later amendments are not shown.

(1)

Within six months of the permanent cessation of commercial operation of the DBS East Project onshore works, an onshore decommissioning plan must be submitted by DBSEL to the relevant planning authority for approval unless otherwise agreed in writing by the relevant planning authority.

(2)

Within six months of the permanent cessation of commercial operation of the DBS West Project onshore works, an onshore decommissioning plan must be submitted by DBSWL to the relevant planning authority for approval unless otherwise agreed in writing by the relevant planning authority.

(3)

Any onshore decommissioning plan submitted under sub-paragraphs (1) or (2) must be approved by the relevant planning authority prior to any decommissioning works commencing unless otherwise agreed in writing between the relevant planning authority and the undertaker.

(4)

If the relevant planning authority fails to notify the undertaker of its decision within 56 days of receiving a request for approval under sub-paragraphs (1) or (2) the relevant planning authority is deemed to have given its approval.

(5)

Any decommissioning plan approved under this requirement must be implemented as approved.