Paragraph 25 Restoration of land used temporarily for construction
Subject to article 30 any land landward of MLWS within the Order limits that is used temporarily for construction of the onshore works, and not ultimately incorporated in permanent works or approved landscaping, must be reinstated to its former condition, or such condition as the relevant planning authority may approve in consultation with, where appropriate, the MMO, and where reinstatement works affect a watercourse, the relevant drainage authority, as soon as reasonably practicable and in any event within twelve months of completion of the relevant phase of the onshore works, or such other period as the relevant planning authority may approve.