Paragraph 96 Access
If in consequence of the agreement reached in accordance with paragraphs 88(1) and 88(2) or the powers granted under this Order the access to any apparatus, the North Humber to High Marnham Site, the Wanlass Beck Site and/or the Birkhill Wood Site is materially obstructed, the undertaker must provide such alternative means of access to such apparatus, the North Humber to High Marnham Site, the Wanlass Beck Site and/or the Birkhill Wood site as will enable National Grid Electricity Transmission Plc to access, maintain or use the apparatus, the North Humber to High Marnham Site, the Wanlass Beck Site and/or the Birkhill Wood site no less effectively than was possible before such obstruction.