(1)

No phase of the onshore works may be commenced until a code of construction practice (which must accord with the outline code of construction practice) for that phase has been submitted to and approved by the relevant planning authority in consultation as appropriate with the Environment Agency, the relevant statutory nature conservation body and the MMO where required.

(2)

A code of construction practice submitted under sub-paragraph (1) may cover one or more phase of the onshore works.

(3)

All construction works for each phase must be undertaken in accordance with the relevant approved code of construction practice.

(4)

Pre-commencement screening and fencing works must only take place in accordance with a specific plan for such pre-commencement works which must accord with the relevant details for screening and fencing security set out in the outline code of construction practice, and which has been submitted to and approved by the relevant planning authority following consultation with the relevant statutory nature conservation body.

(5)

All temporary fencing must be removed on completion of the relevant phase of the onshore works unless otherwise approved by the relevant planning authority.

(6)

All pre-commencement screening and fencing works must be removed on completion of the relevant pre-commencement works unless otherwise approved by the relevant planning authority.