Paragraph 39 Noise restriction
No piling activity can commence within Work Nos. 1B and 4B during the herring spawning season until a herring spawning piling restriction plan (in accordance with the herring spawning plan) is submitted to and approved in writing by the MMO, in consultation with the relevant statutory nature conservation body.
The herring spawning piling restriction plan must be submitted to the MMO no later than six months prior to the commencement of the relevant activities unless otherwise agreed in writing by the MMO.
The herring spawning piling restriction plan must present updated underwater noise modelling, which must be based on final project parameters to be used to install piles and must include details of any mitigation measures to be employed.
If the updated underwater noise modelling referred to in sub-paragraph (3) above demonstrates that noise levels above 135 decibels from any piling area within Work Nos. 1B and/or 4B will impact either or both of—
the area shoreward of the Herring Spawning Noise Restriction Boundary; or
any area within 38km seaward of MHWS,
during the herring spawning season then any piles located within that piling area must not be installed during the herring spawning season without written approval from the MMO.
Any piling activity within Work Nos. 1B and 4B during the herring spawning season must be undertaken in accordance with the approved herring spawning piling restriction plan approved under sub-paragraph (1) or in accordance with any approval given by the MMO under sub-paragraph (4) above.
In this condition—
-
“Herring Spawning Noise Restriction Boundary” means the boundary indicated by the red line on the herring spawning plan, with the restricted area being the area shoreward of this boundary;
-
“herring spawning plan” means the document certified by the Secretary of State as the herring spawning plan for the purposes of the Order under article 42 (certification of plans and documents, etc.) and referenced in Schedule 19 (documents to be certified);
-
“herring spawning season” means 21 August to 30 September inclusive or such other period as agreed in writing with the MMO; and
-
“piling area” means any area within Work Nos. 1B and/or 4B within which one or more piled foundations is proposed to be installed.