Paragraph 16 Pre-commencement, Construction and Operational Drainage Strategy
No phase of the onshore works may be commenced until a written plan for drainage during construction of the relevant phase has been submitted to and approved by the relevant planning authority in consultation with the lead local flood authority, relevant drainage authority and the Environment Agency.
No pre-commencement works may be carried out until a specific written plan for drainage for the relevant pre-commencement works has been submitted to and approved or agreed not required by the relevant planning authority in consultation with the lead local flood authority, relevant drainage authority and the Environment Agency.
No phase of the onshore works may be commenced until a written plan for drainage during operation of the relevant work, has been submitted to and approved by the relevant planning authority in consultation with the lead local flood authority, relevant drainage authority and the Environment Agency.
Each pre-commencement drainage strategy, construction drainage strategy and operational drainage strategy must—
accord with the principles for the relevant phase set out in the outline drainage strategy;
include a timetable for implementation; and
include provision for the maintenance of any measures identified.
Each pre-commencement drainage strategy, construction drainage strategy and operational drainage strategy must be implemented as approved.
A construction drainage strategy and operational drainage strategy submitted under sub-paragraphs (1) and (2) may cover one or more phases.