Paragraph 2 Details of licensed marine activities
Subject to the conditions, this licence authorises the undertaker (and any agent or contractor acting on their behalf) to carry out the following licensable marine activities under section 66(1) (licensable marine activities) of the 2009 Act—
the deposit at sea within the Order limits seaward of MHWS of the substances and objects specified in paragraph 4 below and, when combined with the disposal authorised within disposal ground 1 (DBS East) by the licences granted under Schedules 12, 14 and 14A of the Order, of up to 4,242,327 cubic metres (being a maximum, not an approximate upper figure) of inert material of natural origin produced during construction drilling or seabed preparation for foundation works, cable works and boulder clearance works at disposal site references to be provided to the MMO within disposal ground 1 (DBS East) and any other disposal sites approved in writing by the MMO;
the construction of works in or over the sea or on or under the sea bed;
dredging for the purposes of seabed preparation for foundation works or cable works;
the removal of sediment samples for the purposes of informing environmental monitoring under this licence during pre-construction, construction and operation;
boulder clearance works by displacement ploughing or subsea grab technique or any other comparable method;
removal of static fishing equipment; and
site preparation works.