Paragraph 22 Pre-construction plans and documentation
The licensed activities or any phase of those activities must not commence until the following (insofar as relevant to that activity or phase of activity) have been submitted to and approved in writing by the MMO, in consultation with Trinity House, the MCA, the relevant statutory nature conservation body and UKHO as appropriate—
a layout plan setting out proposed details of the authorised scheme, including the—
number, dimensions, specification, foundation type(s) and depth for each offshore converter platform;
the grid coordinates of the centre point of the proposed location for each wind turbine generator and offshore converter platform;
proposed layout of all cables;
location and specification of all other aspects of the authorised scheme; and
any exclusion zones or micro-siting requirements identified pursuant to sub-paragraph 13(1)(e)(iv) or relating to any habitats of principal importance, Annex I subtidal habitat or surficial deposits of glacial till identified as part of surveys undertaken in accordance with condition 18;
to ensure conformity with the description of Work Nos. 2B, 3B, 7B and 8B and compliance with conditions 1 to 3;
a construction programme and monitoring plan (which accords with the in principle monitoring plan) which, save in respect information submitted pursuant to sub-paragraph (b)(iii)(aa), is to be submitted to the MMO at least six months prior to commencement of licensed activities and to include details of—
the proposed construction start date;
proposed timings for mobilisation of plant, delivery of materials and installation works;
proposed pre-construction surveys, baseline report format and content, construction monitoring, post-construction surveys and monitoring and related reporting in accordance with conditions 18, 19 and 20 to be submitted to the MMO in accordance with the following (unless otherwise agreed in writing with the MMO)—
at least six months prior to the first survey, detail of the pre-construction surveys and an outline of all proposed pre-construction monitoring;
at least six months prior to construction, detail on construction monitoring; and
at least six months prior to commissioning, detail of post-construction (and operational) monitoring;
an indicative written construction programme for all offshore converter platforms and cables including fibre optic cables comprised in the works at Part 1 (licensed marine activities) of this Schedule (insofar as not shown in paragraph (ii) above); and
a monitoring plan for each topic identified, unless otherwise agreed in writing with the MMO, setting out the circumstances in which monitoring will be required and the monitoring to be carried out in such circumstances;
a construction method statement (in accordance with the cable statement), including details of—
cable burial, specification, installation and monitoring to include—
the technical specification of cables below MHWS;
a detailed cable laying plan for the authorised scheme, incorporating a detailed burial risk assessment encompassing the identification of any cable protection that exceeds 5 percent of navigable depth referenced to Chart Datum;
in the event that any area of cable protection exceeding 5 percent of navigable depth is identified, details of any steps (to be determined following consultation with the MCA and Trinity House) to be taken to ensure existing and future safe navigation is not compromised, or similar such assessment to ascertain suitable burial depths and cable laying techniques, including cable protection;
in the event that any area of cable protection exceeding 5 percent of navigable depth is identified within the 10m depth contour closest to the MHWS, details of updated nearshore sediment transport modelling to enable a comparison with the conclusions of the environmental statement to ensure that the impacts of the identified cable protection will not be significantly different to those in the environmental statement; and
proposals for monitoring cables including cable protection until the authorised scheme is decommissioned which includes a risk-based approach to the management of unburied or shallow buried cables;
a scour protection plan (in accordance with the outline scour protection plan) including details of scour protection and cable protection including details of the need, type, sources, quantity and installation methods for scour protection and cable protection, with details updated and resubmitted for approval if changes to it are proposed following cable laying operations;
foundation installation methodology, including drilling methods and disposal of drill arisings and material extracted during seabed preparation for foundation and cable installation works and having regard to any mitigation scheme pursuant to sub-paragraph (1)(i);
advisory safe passing distances for vessels around sites where the licensed activities are taking place;
contractors;
vessels and vessel transit corridors;
associated ancillary works; and
guard vessels to be employed;
a project environmental management plan (in accordance with the outline project environmental management plan) covering the period of construction and operation to include details of—
a marine pollution contingency plan to address the risks, methods and procedures to deal with any spills and collision incidents during construction and operation of the authorised scheme in relation to all activities carried out;
a chemical risk assessment, including information regarding how and when chemicals are to be used, stored and transported in accordance with recognised best practice guidance and standards;
waste management and disposal arrangements;
the appointment and responsibilities of a fisheries liaison officer;
a fisheries liaison and coexistence plan (which accords with the outline fisheries liaison and co-existence plan) to ensure relevant fishing fleets are notified of commencement of licensed activities pursuant to condition 4 and to address the interaction of the licensed activities with fishing activities;
a code of conduct for vessel operators to reduce risk of injury to mammals; and
procedures, which must be adopted within vessel transit corridors to minimise disturbance to red-throated diver during the period 1 November to 31 March (inclusive), which must be in accordance with the best practice protocol for minimising disturbance to red-throated diver;
an archaeological written scheme of investigation in relation to the offshore Order limits seaward of MHWS, which must accord with the outline written scheme of investigation (offshore) and industry good practice, in consultation with the statutory historic body to include—
details of responsibilities of the undertaker, archaeological consultant and contractor;
a methodology for further site investigation including any specifications for geophysical, geotechnical and diver or remotely operated vehicle investigations;
archaeological analysis of survey data, and timetable for reporting, which is to be submitted to the MMO within four months of any survey being completed;
delivery of any mitigation including, where necessary, identification and modification of archaeological exclusion zones;
monitoring of archaeological exclusion zones during and post construction;
a requirement for the undertaker to ensure that a copy of any agreed archaeological report is deposited with the Archaeological Data Service, by submitting an OASIS (‘Online Access to the Index of archaeological investigations’) form with a digital copy of the report within six months of completion of construction of the authorised scheme, and to notify the MMO and Historic England that the OASIS form has been submitted to the Archaeological Data Service within two weeks of submission;
a reporting and recording protocol, including reporting of any wreck or wreck material during construction, operation and decommissioning of the authorised scheme; and
a timetable for all further site investigations, which must allow sufficient opportunity to establish a full understanding of the historic environment within the offshore Order limits and the approval of any necessary mitigation required as a result of the further site investigations prior to commencement of licensed activities;
an aids to navigation management plan to be agreed in writing by the MMO following consultation with Trinity House, the MCA, the Civil Aviation Authority and UKHO specifying how the undertaker will ensure compliance with condition 8 from the commencement of construction of the authorised scheme to the completion of decommissioning;
in the event that driven or part-driven pile foundations are proposed to be used, a marine mammal mitigation protocol (in accordance with the outline marine mammal mitigation protocol), the intention of which is to prevent injury to marine mammals, following current best practice as advised by the relevant statutory nature conservation bodies and which must include details of noise reduction methods through project design (primary measures) and/or, deployment of noise mitigation systems or noise abatement systems (secondary measures) that will be utilised to manage sounds from those piling activities and such protocol must include full details and justification for the mitigation chosen or excluded for deployment;
a navigation management plan to manage crew transfer vessels (including daughter craft) during the construction and operation of the authorised scheme;
a final cable statement (in accordance with the cable statement); and
a site specific chemical risk assessment, which must be submitted no later than ten weeks prior to use of the relevant chemical, for all chemicals (with the exception of chemicals present on the OSPAR List of Substances Used and Discharged Offshore which Are Considered to Pose Little or No Risk to the Environment) that have a pathway to the marine environment used for the marine licensed activities, outside the course of normal navigation, to include—
the function of the chemical,
the quantities being used and the frequency of use; and
the physical, chemical, and ecotoxicological properties of the chemical.
Pre-commencement surveys and archaeological investigations and pre-commencement material operations which involve intrusive seabed works must only take place in accordance with a specific outline written scheme of investigation (which must accord with the details set out in the outline written scheme of investigation (offshore)) which has been submitted to and approved by the MMO.
Anchoring of vessels must not occur within the Holderness Inshore Marine Conservation Zone or within the Smithic Bank, unless otherwise agreed in writing with the MMO following consultation with the relevant statutory nature conservation body and in the event that jack-up vessels are proposed to be used for cable installation or maintenance, their legs must not be deployed within the Holderness Inshore Marine Conservation Zone or within the Smithic Bank, unless otherwise agreed in writing with the MMO following consultation with the relevant statutory nature conservation body. For the purposes of this sub-paragraph the “Holderness Inshore Marine Conservation Zone” and the “Smithic Bank” means the area bounded by the following coordinates—
| Co-ordinate ID | X | Y | Co-ordinate ID | X | Y |
|---|---|---|---|---|---|
| 1 | 295623.5 | 5988145 | 23 | 298275.5 | 5998380 |
| 2 | 295151.2 | 5988060 | 24 | 298621.2 | 5998874 |
| 3 | 294745.5 | 5988423 | 25 | 298836.9 | 5999246 |
| 4 | 294511.3 | 5988778 | 26 | 299247.9 | 5999525 |
| 5 | 294268.6 | 5989292 | 27 | 299486.8 | 5999430 |
| 6 | 293876.3 | 5989601 | 28 | 299598.1 | 5998762 |
| 7 | 293560.8 | 5989880 | 39 | 299594.8 | 5997967 |
| 8 | 293332.8 | 5990368 | 30 | 299268.7 | 5997636 |
| 9 | 293232.9 | 5990929 | 31 | 298936.8 | 5997174 |
| 10 | 293248 | 5991618 | 32 | 298720.2 | 5996494 |
| 11 | 293357 | 5992382 | 33 | 298564.6 | 5995785 |
| 12 | 293486 | 5993034 | 34 | 298381.8 | 5994812 |
| 13 | 293672.5 | 5993577 | 35 | 298391.6 | 5993963 |
| 14 | 293869.5 | 5994077 | 36 | 298294.2 | 5992800 |
| 15 | 294131.6 | 5994638 | 37 | 298298.3 | 5991819 |
| 16 | 294494.2 | 5995216 | 38 | 298274.7 | 5990919 |
| 17 | 295039.8 | 5995701 | 39 | 298010.4 | 5989870 |
| 18 | 295805.2 | 5996367 | 40 | 297423.3 | 5988941 |
| 19 | 296495.2 | 5996740 | 41 | 296719 | 5988548 |
| 20 | 297164.8 | 5997219 | 42 | 296143.8 | 5988255 |
| 21 | 297591.3 | 5997561 | 43 | 295623.5 | 5988145 |
| 22 | 297845.4 | 5997953 |
Any sediment removed from within the Dogger Bank Special Area of Conservation during construction of the authorised scheme must be disposed of within that part of the Dogger Bank Special Area of Conservation which falls within the Order limits.
In the event that driven or part-driven pile foundations are proposed to be used, the hammer energy used to drive or part-drive monopile foundations must not exceed 6,000kJ and the hammer energy used to drive or part-drive pin pile foundations must not exceed 3,000kJ.
The maximum number of main vessels engaged at any time in activities related to piling for the licensed activities when combined with the number of main vessels engaged in piling activities authorised by the licences granted under Schedules 10 to 12 must not exceed 2 vessels.
The number of piled foundations installed within a 24-hour period when combined with the number of piled foundations installed pursuant to the licences granted under Schedules 10 to 12 of the Order within the same 24-hour period must not exceed—
4 monopile foundations;
8 pin pile foundations;
3 monopile foundations and 2 pin pile foundations;
2 monopile foundations and 4 pin pile foundations; or
1 monopile foundation and 6 pin pile foundations.
The number of piled foundations installed concurrently when combined with the number of piled foundations installed concurrently pursuant to the licences granted under Schedules 10 to 12 must not exceed—
where only monopile foundations are being installed concurrently 2 monopile foundations;
where only pin pile foundations are being installed concurrently 2 pin pile foundations; and
where a combination of monopile foundations and pin pile foundations are being installed concurrently 1 monopile foundation and 1 pin pile foundation.
In sub-paragraphs 13(1)(d)(ii) and 13(1)(j) above—
-
“pathway to the marine environment” means open systems or closed systems that require top up;
-
“chemicals” comprise both substances and preparations;
-
“preparation” means a mixture or solution composed of two or more substances; and
-
“substance” means a chemical element and its compounds in the natural state or obtained by any manufacturing process, including any additive necessary to preserve its stability and any impurity deriving from the process used, but excluding any solvent which may be separated without affecting the stability of the substance or changing its composition.