Paragraph 14 Maintenance of the authorised scheme

Original text. Later amendments are not shown.

(1)

The undertaker may at any time maintain the authorised scheme, except to the extent that this licence or an agreement made under this licence provides otherwise.

(2)

Maintenance works include but are not limited to—

(a)

routine maintenance of wind turbine generators, offshore converter platforms, and their respective foundations;

(b)

major offshore converter platform replacement;

(c)

painting and applying other coatings to offshore converter platforms;

(d)

bird waste and marine growth removal;

(e)

surveys/inspections of cables;

(f)

cable remedial burial;

(g)

cable protection replenishment;

(h)

cable repairs and replacement;

(i)

access ladder and boat landing replacement;

(j)

offshore converter platform anode replacement; and

(k)

J-tube repair/replacement.

(3)

Operation of the licensed activities must not commence until an offshore operations and maintenance plan substantially in accordance with the outline offshore operations and maintenance plan has been submitted to and approved in writing by the MMO. The operations and maintenance plan must include, but is not limited to—

(a)

a list of maintenance activities within the marine environment that are planned for the lifetime of the licensed activities;

(b)

details of the typical construction plant, machinery and personnel requirements for each maintenance activity and any requirements for detailed method statements;

(c)

details of the typical frequency and timing of each maintenance activity; and

(d)

details of controls and mitigation that will be in place in order to protect the marine environment.

(4)

The offshore operations and maintenance plan must be reviewed every three years commencing from the date on which the plan was approved, unless otherwise agreed by the MMO, to ensure the details of the maintenance activities remain accurate. The conclusions of that review must be submitted to and approved by the MMO in writing.

(5)

The offshore operations and maintenance plan must be implemented as approved by the MMO.

(6)

Unless otherwise agreed in writing with the MMO, the undertaker must submit—

(a)

the first offshore operations and maintenance plan at least 6 months prior to the operation of the licensed activities;

(b)

any revised offshore operations and maintenance plan submitted in accordance with sub-paragraph (4) at least 6 months before such revised plan is required to be put in place; and

(c)

where additional maintenance activities are identified that are not included in the approved offshore operations and maintenance plan, or any revised plan approved in accordance with sub-paragraph (4), an updated offshore operations and maintenance plan including the additional maintenance activities must be submitted to and approved by the MMO in writing as soon as possible after the need for such additional maintenance activities is identified.