Paragraph 83 Shared area works
Any approval of National Grid Electricity Transmission Plc required under this Schedule—
must not be unreasonably withheld or delayed;
in the case of a refusal must be accompanied by a statement of grounds or refusal;
may be given subject to such reasonable requirements as National Grid Electricity Transmission Plc may have in connection with the safe, economic and efficient construction, commissioning, operation, maintenance and future decommissioning of the North Humber to High Marnham Project, the Wanlass Beck Project and/or the Birkhill Wood Project or otherwise for the protection of the North Humber to High Marnham apparatus, the Wanlass Beck apparatus and/or the Birkhill Wood Project apparatus;
provided always that in relation to a refusal under paragraph (b) or any requirements requested pursuant to paragraph (c) the undertaker shall be permitted to refer such matters to dispute resolution pursuant to paragraph 97; and
National Grid Electricity Transmission Plc must employ reasonable endeavours to respond to the submission of any plans within a period of 56 days from the date of submission of the plans. If National Grid Electricity Transmission Plc require further particulars, such particulars must be requested by National Grid Electricity Transmission Plc no later than 21 days from the submission of plans and thereafter National Grid Electricity Transmission Plc must employ reasonable endeavours to respond to the submission within 56 days from receipt of the further particulars.