(1)

No wind turbine generator forming part of Work No. 1B is permitted to rotate its rotor blades on its horizontal axis until the undertaker has submitted a Radar Mitigation Scheme to the Secretary of State and the Secretary of State, having consulted with the Ministry of Defence, confirms satisfaction in writing to the undertaker that appropriate mitigation will be implemented and maintained for the life of the authorised development and that arrangements have been put in place with the Ministry of Defence to ensure that the approved mitigation is implemented and maintained for the life of the DBS West Project offshore works.

(2)

The undertaker must thereafter comply with all obligations contained within the approved mitigation for the life of the DBS West Project offshore works.

(3)

For the purposes of this requirement—

  • “appropriate mitigation” means measures to prevent or remove any adverse effects which the DBS West Project Offshore works will have on the air defence radar(s) at Remote Radar Head (RRH) Staxton Wold, and the Ministry of Defence’s air surveillance and control operations;

  • “approved mitigation” means the detailed Radar Mitigation Scheme (RMS) that will set out the appropriate mitigation and timescales for implementation as agreed with the Ministry of Defence at the time the Secretary of State confirms satisfaction in writing in accordance with sub-paragraph (1); and