An application has been made to the Secretary of State under paragraph 2 of Schedule 6 to the Planning Act 2008f1, in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011f2 (“the 2011 Regulations”) for a non-material change to the Dogger Bank Teesside A and B Offshore Wind Farm Order 2015f3 (“the 2015 Order”).

The Secretary of State, having considered the application and the responses to the publicity and consultation carried out in accordance with regulations 6 and 7 of the 2011 Regulations, has decided to make this Order amending the 2015 Order.

Accordingly, the Secretary of State, in exercise of the powers in paragraph 2(1) and (9) of Schedule 6 to the Planning Act 2008, makes the following Order.

Annotations to the whole text

Footnotes

f1

2008 c. 29. Paragraph 2 was amended by paragraphs 1 and 72 of Schedule 13 to the Localism Act 2011 (c. 20), and by section 28 of the Infrastructure Act 2015 (c. 7). There are other amendments to the Act which are not relevant to this Order.

f2

S.I. 2011/2055. Relevant amendments to this instrument were made by S.I. 2012/635, S.I. 2012/2654, S.I. 2012/2732, S.I.2013/522, S.I. 2013/755, S.I. 2015/760, S.I. 2017/314, S.I. 2017/524, S.I. 2018/378, S.I. 2019/734 and S.I. 2020/1534.

f3

S.I. 2015/1592, as amended by S.I. 2019/669, S.I. 2020/851, S.I. 2020/1389, S.I.2021/39 and S.I. 2021/71.

Contents

  1. 1Citation and commencement
  2. 2Amendment to the Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
  3. 3Amendment to Part 3 (requirements) of Schedule 1 (authorised project)
  4. Signature
  5. Explanatory note

1Citation and commencement

This Order may be cited as the Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2024 and comes into force on 12thNovember 2024.

2Amendment to the Dogger Bank Teesside A and B Offshore Wind Farm Order 2015

The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015 is amended in accordance with this Order.

3Amendment to Part 3 (requirements) of Schedule 1 (authorised project)

In Part 3 (requirements) of Schedule 1 (authorised project), in paragraph 5(8)(b) for “1,900 kilojoules” substitute “3,000 kilojoules”.

Signature

Signed by authority of the Secretary of State for Energy Security and Net Zero

John Wheadon

Head of Energy Infrastructure Planning Delivery

Department for Energy Security and Net Zero

11th November 2024

Explanatory note

(This note is not part of the Order)

This Order amends the Dogger Bank Teesside A and B Offshore Wind Farm Order 2015, a development consent order under the Planning Act 2008, following an application made in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 for a non-material change under paragraph 2 of Schedule 6 to the Planning Act 2008. This Order increases the maximum hammer energy limit from 1,900 kJ to 3,000 kJ for pin-piles required to install the Offshore Platform within Project A.