Paragraph 36 Restoration of land used temporarily for constructionI1
England, Wales and Scotland
Subject to article 29 (temporary use of land for carrying out authorised project), any land landward of MLWS within the Order limits that is used temporarily for construction of the relevant stage of the onshore works, and not ultimately incorporated in permanent works or approved landscaping, must be reinstated to its former condition, or such condition as the relevant planning authority may approve, within 6 months of completion of the onshore works, or such other period as the relevant planning authority may approve.
Annotations
Commencement
- I1
Sch. 1 Pt. 3 para. 36 in force at 26.8.2015, see art. 1