Paragraph 11 I1
England, Wales and Scotland
In the case of protective works of which the Company has informed the undertaker in writing as mentioned in paragraph 10, the undertaker must comply with all reasonable requirements of the Company arising from its inspection under paragraph 9 as promptly as practicable after the undertaker has been notified of such requirements.
Annotations
Commencement
- I1
Sch. 12 Pt. 4 para. 11 in force at 26.8.2015, see art. 1