Paragraph 2 I1
England, Wales and Scotland
In this Part—
“Agency” means the Environment Agency;
“construction” includes execution, placing, altering, replacing, relaying and removal; and “construct” and “constructed” must be construed accordingly;
“drainage work” means any watercourse and includes—
- (a)
any land that provides or is expected to provide flood storage capacity for any watercourse;
- (b)
any bank, wall, embankment or other structure, or any appliance, constructed or used for land drainage, flood defence or tidal monitoring; and
- (c)
any ancillary works constructed as a consequence of works carried out for drainage purposes;
- (a)
“fishery” means any watercourse within the Order limits containing fish, fish in such waters and the spawn, habitat or food of such fish;
“plans” includes sections, drawings, specifications and method statements;
“specified work” means so much of any work or operation authorised by this Order as is in, on, under, over or within 16 metres of, a drainage work or is otherwise likely to—
- (a)
affect any drainage work or the volumetric rate of flow of water in or flowing to or from any drainage work;
- (b)
affect the flow, purity or quality of water in any watercourse or other surface waters or ground water;
- (c)
cause obstruction to the free passage of fish or damage to any fishery; or
- (d)
affect the conservation, distribution or use of water resources;
- (a)
“watercourse” means all rivers, streams, ditches, drains, cuts, culverts, dykes, sluices, sewers and passages through which water flows except a public sewer.
Annotations
Commencement
- I1