Paragraph 7 I1
England, Wales and Scotland
Subject to paragraph 9, if by reason of the construction of any specified work or of the failure of any such work the efficiency of any drainage work for flood defence purposes is impaired, or the drainage work is otherwise damaged, such impairment or damage must be made good by the undertaker to the reasonable satisfaction of the Agency, and, if the undertaker fails to do so, the Agency may make good the same and recover from the undertaker the expense reasonably incurred by it in doing so.
Annotations
Commencement
- I1
Sch. 12 Pt. 5 para. 7 in force at 26.8.2015, see art. 1