(1)

Before carrying out any maintenance works affecting access rights over the Wilton Complex, the undertaker must prepare a draft maintenance access plan and publicise and consult on the draft plan with owners and operators in the Wilton Complex.

(2)

The undertaker must take account of the responses to consultation referred to in sub-paragraph (1) before approving the maintenance access plan.

(3)

No works affecting access rights over the Wilton Complex may commence until 30 days after a copy of the approved maintenance access plan is served on owners and operators in the Wilton Complex.

(4)

On the reasonable and evidenced request of an owner or operator in the Wilton Complex affected by proposed works, the undertaker must extend the period mentioned in sub-paragraph (3) by a reasonable time.