Regulation 9 Plants used to generate heat before the first commissioning dateI1

England, Wales and Scotland

(1)

The requirements referred to in regulation 3(b) are that no part of the plant which generates heat, other than any of the components listed in paragraph (2), was used before the plant’s first commissioning date.

(2)

The components referred to in paragraph (1) are—

F1(a)

components, apart from solar thermal collectors (liquid filled flat plate or evacuated tubes), which solely generate heat for the purpose of heating domestic hot water;

(b)

supplementary electric heaters; and

(c)

circulation pumps.

Annotations

Textual amendments

F1

Reg. 9(2)(a) substituted (24.3.2016) by The Renewable Heat Incentive Scheme and Domestic Renewable Heat Incentive Scheme (Amendment) Regulations 2016 (S.I. 2016/257), regs. 1, 18

Commencement

I1

Reg. 9 in force at 9.4.2014, see reg. 1