Paragraph 1 I1
England, Wales and Scotland
The requirements set out in this Schedule in relation to a property are that an Energy Performance Certificate (“EPC”) has been issued for the property on the basis that it consists of a dwelling and—
the property is an eligible new-build property; or
the requirements in—
sub-paragraph (2) are met; and
either sub-paragraph (3) or (4) are met.
The requirements referred to in sub-paragraph (1)(b)(i) are that—
the property was first occupied before the first commissioning date for the plant; and
the period between the date on which the EPC was issued and the RHI date is less than 24 months.
The requirements referred to in sub-paragraph (1)(b)(ii) are that the EPC—
does not include a recommendation report; or
includes a recommendation report which does not recommend that loft insulation or cavity wall insulation be installed.
The requirements referred to in sub-paragraph (1)(b)(ii) are that loft insulation or cavity wall insulation is recommended in a recommendation report included in the EPC and cannot be installed in accordance with that recommendation as that installation—
is prevented by restrictions on the building as a consequence of its status as a listed building, its location in a conservation area or the material impact that such installation would have on a protected species;
would otherwise be unlawful; or
is not feasible due to atypical local environmental conditions or the structure of the property.
Annotations
Textual amendments
- F1
Sch. 3 para. 1(2) substituted (24.3.2016) by The Renewable Heat Incentive Scheme and Domestic Renewable Heat Incentive Scheme (Amendment) Regulations 2016 (S.I. 2016/257), regs. 1, 26
Commencement
- I1
Sch. 3 para. 1 in force at 9.4.2014, see reg. 1