OpenLegislation

Regulation 20 Applicable area rate

Original text. Later amendments are not shown.

(1)

This regulation applies for the purposes of determining the applicable area rate under the formula in regulation 16(2).

(2)

The “applicable area rate”, in relation to a relevant residential building, means—

(a)

if the previous development condition in paragraph (3) is met in respect of the chargeable application, the area rate in relation to the collecting authority for the relevant residential building shown in column 2 of the table in Schedule 3, and

(b)

in any other case, the area rate in relation to the collecting authority for the relevant residential building shown in column 3 of the table in Schedule 3.

(3)

The “previous development condition” is that—

(a)

the building work to which the chargeable application relates is to be carried out in relation to development for which planning permission is granted by the Town and Country Planning (General Permitted Development) (England) Order 2015f1, or

(b)

the building work to which the application relates is to be carried out on a previously developed site (as defined in regulation 21).

Annotations

Footnotes

f1

S.I. 2015/596, which has been amended by S.I. 2016/332, 2016/765, 2016/772, 2016/1040, 2016/1154, 2017/391, 2017/571, 2017/619, 2017/1011, 2017/1012, 2018/119, 2018/343, 2018/695, 2019/907, 2020/330, 2020/412, 2020/632, 2020/755, 2020/756, 2020/1243, 2020/1459, 2021/428, 2021/467, 2021/814, 2021/1464, 2022/278, 2023/747, 2023/1279 and 2024/141.