The Climate Change Levy (Combined Heat and Power Stations) Regulations 2005
Draft 2005, ISBN 0110724747
Draft Regulations laid before Parliament under section 30 of and Schedule 6, paragraph 146(3) to the Finance Act 2000, for approval by resolution of the House of Commons.
CLIMATE CHANGE LEVY
Made 2005
Coming into force in accordance with regulation 1
The Treasury, in exercise of the powers conferred by section 30 of and Schedule 6, paragraphs 15(4), 16(2), 16(3), 146(7), 147, 148(4), 148(7), 148(8), 148(9), 149(1), 149(2) and 149(3) to the Finance Act 2000f1, make the following Regulations, a draft of which has, in accordance with paragraph 146(3) of that Schedule, been laid before Parliament and approved by a resolution of the House of Commons:
Annotations to the whole text
Footnotes
- f1
-
2000 c. 17; paragraphs 15, 148 and 149 are amended by the Finance Act 2003 (c. 14) sections 189 and 216 and Schedule 43 Part 4 in relation to supplies made on or after such day as the Treasury may by order made by statutory instrument appoint (about which, see S.I. 2005/XXXX (C. XX)).
Contents
- 1Preliminary
- 2Preliminary
- 3Supplies to combined heat and power stations: exemption for inputs
- 4Supplies from partly exempt combined heat and power stations: exemption for outputs
- 5Fully exempt combined heat and power stations: conditions to be satisfied for full-exemption certificate
- 6Transitional provisions: inputs efficiency percentage and outputs partly exempt limit
- 7Transitional provisions: inputs efficiency percentage and outputs partly exempt limit
- 8Revocations
- Signature
- Explanatory note
1Preliminary
These Regulations may be cited as the Climate Change Levy (Combined Heat and Power Stations) Regulations 2005 and shall come into force on the day after the day on which they are made.
2Preliminary
In these Regulations—
-
“the Act” refers to Schedule 6 to the Finance Act 2000f1;
-
“CCL” refers to climate change levy;
-
“CHPQA” refers to the Combined Heat and Power Quality Assurance Standard, Issue 1, November 2000 originally published by the Department for the Environment, Transport and the Regions (the “Standard”) (including the later of version Final 1.0 or 2.0 of CHPQA Guidance Notesf2 0 to 4 (including 2(S), 3(S) and 4(S)), 10 to 28 and 30);
-
“station” refers to a combined heat and power station or, in appropriate circumstances, to combined heat and power stations forming at least part of a single CHP Scheme.
But, for the purposes of regulation 3(2), “CHPQA” refers to the current issue of that Standard and current versions of those and any subsequent Guidance Notes.
An issue or version is current for these purposes to the extent that it is neither varied, replaced nor revoked by another issue or version.
These Regulations must be applied in a way consistent with the CHPQA and paragraph (2).
But, for the purposes of regulations 3(2) and 4, any reference in the CHPQA to any relevant “registered” quantity (whether or not mentioned in either regulation) must be treated as a reference to the actual quantity of that name for determination and calculation in accordance with the CHPQA.
That determination and calculation must be on the basis of events in relation to the given station during the given Annual Operation (for “Annual Operation”, see CHPQA Section 4 – 1st January to 31st December).
3Supplies to combined heat and power stations: exemption for inputs
A station’s threshold efficiency percentage is set as 20 per cent (see paragraphs 15(2)(b), 15(3)(b) and 15(4)(a) of the Act).
A station’s efficiency percentage for a given Annual Operation is its Power Efficiency in relation to that Operation (see paragraphs 15(4)(b), 149(1) and 149(2)(e) of the Actf1 and Section 5.6 of the Standard).
4Supplies from partly exempt combined heat and power stations: exemption for outputs
The limit (see paragraph 16(2) of the Act) on the quantity of electricity that may be produced in and supplied from a partly exempt station exempt from CCL for a given Annual Operation is its CHP Qualifying Power Output in relation to that Operation (see Section 5.8 of the Standard).
5Fully exempt combined heat and power stations: conditions to be satisfied for full-exemption certificate
The condition to be satisfied in relation to a station for the purpose of the Secretary of State giving a full-exemption certificate is as follows (see paragraph 148(4) of the Act).
The station’s Quality Index as determined and calculated in accordance with the CHPQA must at least meet the Threshold Quality Index Criterion specified for that station in the CHPQA (see Sections 5.5 and 4 of the Standard).
6Transitional provisions: inputs efficiency percentage and outputs partly exempt limit
Paragraph (2) applies only if regulations 2(2) and 2(3) result in more than one issue of the Standard or version of a Guidance Note being current during the Annual Operation in question and, if they are treated as separately current for the whole Annual Operation, this yields different efficiency percentages for the purposes of regulation 3(2).
The efficiency percentage in regulation 3(2) is then the weighted mean of those different efficiency percentages.
The weighting must reflect the proportion of fuel input to the station during the period in relation to which the relevant issue or version is current.
That proportion must be calculated relative to the station’s actual total fuel input for the Annual Operation in question.
7Transitional provisions: inputs efficiency percentage and outputs partly exempt limit
Paragraph (2) applies only if regulation 4 results in a limit (“A”) for calendar year 2005 that is less than the limit (“B”) that would have applied for that year under regulation 5(2) of the Climate Change Levy (Combined Heat and Power Stations) Prescribed Conditions and Efficiency Percentages Regulations 2001f1.
The limit in regulation 4 for 2005 is then the following sum.
-
X = 365 - Y
-
Y = the number of days elapsed for 2005 up to and including the day these Regulations are made.
8Revocations
The Climate Change Levy (Combined Heat and Power Stations) Prescribed Conditions and Efficiency Percentages Regulations 2001 and the Climate Change Levy (Combined Heat and Power Stations) Prescribed Conditions and Efficiency Percentages (Amendment) Regulations 2003f1 are revoked.
Signature
Two of the Lords Commissioners of Her Majesty’s Treasury
2005
Explanatory note
(This note is not part of the Regulations)
Input fuel to all certified stations
The actual amount of exemption depends on the ratio between a station’s efficiency percentage and the relevant threshold efficiency percentagef5. Regulation 3(2) provides for a station’s efficiency percentage in relation to a given calendar year to be determined in accordance with methodology described in detail in the Combined Heat and Power Quality Assurance Standard, Issue 1, November 2000 originally published by the Department for the Environment, Transport and the Regions (the Standard)f6, f7, f8.
Output electricity from partly exempt stations
Electricity may be supplied from partly exempt stations free from CCL, but only up to a specified limit. Regulation 4 specifies the current calendar year’s annual limit as the station’s CHP Qualifying Power Output in relation to that year in accordance with the Standardf9.
Condition for full-exemption certificate
Regulation 5 prescribes as a condition that the station’s Quality Index measured in accordance with the Standard must at least meet a Threshold Quality Index Criterion specified by the Standard.
Regulatory impact assessment
A full regulatory impact assessment has not been produced for this instrument as it has no impact on the costs of business, charities or voluntary bodies.