(1)

This article applies to a public body or undertaking (“A”) which—

(a)

during a qualifying year of a phase is supplied with electricity measured by a settled half hourly meter; and

(b)

is not required to register, or is not a member of a group required to register, as a participant.

(2)

For the purposes of paragraph (1), A is supplied with electricity where that supply is made in accordance with sections 1 to 3 of Schedule 1.

(3)

A must provide to the administrator in respect of the qualifying year of a phase the information described in paragraph (4) and do so in respect of—

(a)

the first phase, on or before 30th September 2010; and

(b)

the second and subsequent phases, within 6 months of the beginning of the phase.

(4)

The information referred to in paragraph (3) is—

(a)

the information in paragraph 2 of Schedule 5, as applicable to A;

(b)

a list of the settled half hourly meters which measure the supply of electricity to A and the identification numbers of those meters; and

(c)

in respect of the supply of electricity to A measured by settled half hourly meters and non-settled half hourly meters—

(i)

whether or not the supply equalled or exceeded 3000 MWh and, if it did, the amount of the supply; and

(ii)

if the supply exceeded 6000 MWh, why A is not required to register as a participant and which deductions, if any, under section 4 or 5 of Schedule 1 apply.

(5)

Unless otherwise agreed by the administrator, the information must be provided using the Registry.