OpenLegislation

Paragraph 20 Un-metered transport supply: electricity

Original text. Later amendments are not shown.

(1)

Sub-paragraph (2) applies where—

(a)

A has consumed a supply of electricity for the purposes of transport; and

(b)

part of that supply so consumed was not measured by a meter of any sort (“un-metered electricity transport supply”).

(2)

Where this sub-paragraph applies, A may decide that un-metered electricity transport supply is not consumed for the purposes of transport.

(3)

A decision made under sub-paragraph (2)—

(a)

may be made in respect of—

(i)

qualifying electricity in the qualification year of a phase and where so made, applies also to supplies of electricity during the phase;

(ii)

a phase where it was not made in respect of the qualification year, where such a decision is made on or before the participant submits its footprint report;

(b)

must not be altered during the phase.