Paragraph 20 Un-metered transport supply: electricity
Sub-paragraph (2) applies where—
A has consumed a supply of electricity for the purposes of transport; and
part of that supply so consumed was not measured by a meter of any sort (“un-metered electricity transport supply”).
Where this sub-paragraph applies, A may decide that un-metered electricity transport supply is not consumed for the purposes of transport.
A decision made under sub-paragraph (2)—
may be made in respect of—
qualifying electricity in the qualification year of a phase and where so made, applies also to supplies of electricity during the phase;
a phase where it was not made in respect of the qualification year, where such a decision is made on or before the participant submits its footprint report;
must not be altered during the phase.