Article 21 House in-fill measures
A measure (“measure Y”) is a “house in-fill measure” and meets the condition in this article if—
it is installed at domestic premises—
that are not in a block of flats; and
for which the pre-installation SAP band is band D, E, F or G;
it is solid wall insulation;
it is linked with three other measures (“the primary measures”) which are—
solid wall insulation;
promoted by the same participant that promoted measure Y; and
installed at three separate domestic premises on the same street as measure Y; and
For the purposes of paragraph (1)(c), measure Y is linked with the primary measures if—
measure Y is completed during the three month period beginning with the day on which the last of the primary measures is completed;
measure Y is notified under article 25 on the same day as, or after, the notification of the primary measures under that article;
when notifying measure Y under article 25, the participant includes information sufficient to enable the Administrator to identify the primary measures with which it is to be linked; and
none of the primary measures are already linked with another in-fill measure.
In this article, “block of flats” has the same meaning as in article 20(3).