Regulation 27 Non-completion fees: modifications
The modifications in paragraph (2) apply in respect of—
the conditional agreement auction, including the rights and obligations arising out of, or in relation to, this auction; and
capacity agreements that existed on 15th November 2018.
Regulation 43A (non-completion fee) of the Principal Regulations applies as if in paragraph (6)—
in paragraph (a), “; and” were omitted;
in paragraph (b), for “.” there were inserted “; and”; and
after paragraph (b), there were inserted—
“(c)if a non-completion notice is issued during the standstill period, a direction to the Delivery Body to withdraw the termination notice and to terminate a capacity agreement on the ground specified in capacity market rules is to be construed as a reference to a direction to the Delivery Body to withdraw the non-completion notice.”.