OpenLegislation

Paragraph 15 Other emissions activities: activities not previously subject to regulation

Original text. Later amendments are not shown.

(1)

Subject to sub-paragraphs (3) and (4), regulation 7 of the 2018 Regulations applies to the activities listed in column 1 of Table 1 from the date specified in column 2.

(2)

An application for an authorisation for an activity listed in column 1 of Table 1—

(a)

for activities described in paragraph 1 (combustion plant generating electricity in aggregate over 1 MW)—

(i)

may only be made on or after 28 February 2028, and

(ii)

must be received by SEPA by 30 June 2028,

(b)

for any other activity listed in column 1 of Table 1 may only be made on or after the date falling 4 months before the specified date for that activity in column 2.

(3)

Where an application for authorisation is received in accordance with sub-paragraph (2), and is not determined on or before the specified date for that activity, regulation 7 of the 2018 Regulations only applies from the date the application is determined.

(4)

This paragraph does not apply to activities meeting the description of activities listed in column 1 of Table 1 where that activity is, immediately before the relevant date, subject to regulation under the 2012 Regulations.

Table 1

Other emissions activities in Part 3 of schedule 26 of the 2018 RegulationsSpecified date
Activities described in paragraph 1 (combustion plants generating electricity in aggregate over 1 MW)1 January 2029
Activities described in paragraph 68 (other carbon capture activities)1 April 2027
Activities described in paragraph 69 (non-waste anaerobic digestion)1 April 2028