OpenLegislation

Paragraph 16 Other emissions activities: medium combustion plants

Original text. Later amendments are not shown.

(1)

Subject to sub-paragraph (4), regulation 7 of the 2018 Regulations does not apply to the operation of an existing medium combustion plant with a rated thermal input equal to or greater than 1 and less than or equal to 5 megawatts until 1 January 2029.

(2)

Paragraphs 8, 9 and 11 to 13 of schedule 27 of the 2018 Regulations apply to the operation of an existing medium combustion plant with a rated thermal input equal to or greater than 1 and less than or equal to 5 megawatts on or after 1 January 2030.

(3)

An application under the 2018 Regulations to operate an existing medium combustion plant where the rated thermal input of the plant is equal to or greater than 1 and less than or equal to 5 megawatts—

(a)

may only be made on or after 28 February 2028, and

(b)

must be received by SEPA by 30 June 2028.

(4)

Where an application is made in accordance with sub-paragraph (3), regulation 7 of the 2018 Regulations only applies from the date the application is determined.