Interpretation of Part A(1) Interpretation of Part A(1)
(a)
Melting, including making alloys, of non-ferrous metals, including recovered products (refining, foundry casting, etc.) where—
(i)
the plant has a melting capacity of more than 4 tonnes per day for lead or cadmium or 20 tonnes per day for all other metals, and no furnace (other than a vacuum furnace), bath or other holding vessel used in the plant for the melting has a design holding capacity of 5 or more tonnes; or
(ii)
the plant uses a vacuum furnace of any design holding capacity.