The Heat Networks (Supply Targets) (Scotland) Regulations 2023
Draft 2023, ISBN 9780111058206
Draft Regulations laid before the Scottish Parliament under section 99(2) of the Heat Networks (Scotland) Act 2021 for approval by resolution of the Scottish Parliament.
Heat Networks
Made 2023
Coming into force 2023
The Scottish Ministers make the following Regulations in exercise of the powers conferred by section 92(5) of the Heat Networks (Scotland) Act 2021f1 and all other powers enabling them to do so.
In accordance with section 99(2) of the Heat Networks (Scotland) Act 2021, a draft of this instrument has been laid before and approved by the Scottish Parliament.
Annotations to the whole text
Footnotes
- f1
Contents
- 1Citation and commencement
- 2Modification of section 92(1) - heat network supply targets
- Signature
- Explanatory note
1Citation and commencement
These Regulations may be cited as the Heat Networks (Supply Targets) (Scotland) Regulations 2023 and come into force on the day after the day on which they are made.
2Modification of section 92(1) - heat network supply targets
Section 92(1) (heat networks supply targets) of the Heat Networks (Scotland) Act 2021 is modified as specified in paragraph (2).
After paragraph (b) insert—
“(c)7 terawatt hours of output by 2035.”.
Signature
Name
Authorised to sign by the Scottish Ministers
St Andrew’s House,
Edinburgh
Date
Explanatory note
(This note is not part of the Regulations)
These Regulations make provision under the Heat Networks (Scotland) Act 2021 (the “Act”) and come into force on the day after the day on which they are made.
Regulation 2 of these Regulations modifies section 92(1) of the Act to specify an additional target relating to output from the combined supply of thermal energy by heat networks in Scotland to be reached by 2035. Output must reach at least 7 terawatt hours.