Regulation 45 Permits: proposed change in operation
An operator of an installation or mobile plant in respect of which a permit is granted must give notice to SEPA of a proposed change in operation (a “change notice”) at least 14 days before making the change.
A change notice must—
be in writing, and
contain a description of the proposed change in operation.
SEPA must acknowledge receipt of a change notice.
A change notice is not necessary if—
the operator applies for a variation of the permit before a change in operation is made, and
that application describes the proposed change.
An operator must not make a change during any period beginning with the date of service on the operator of a notice under regulation 63(2) and ending on the date on which the operator provides the required information.