Article 11 Determining the number of renewables obligation certificates to be produced in an obligation period

Original text. Later amendments are not shown.

(1)

Following the determination of calculations A, B and C for an obligation period, the Department is to determine the total number of renewables obligation certificates required to be produced by designated suppliers (“the total obligation”) for that period in accordance with paragraphs (2) to (5).

(2)

Where calculation A is greater than calculation B for an obligation period, the total obligation for that period is calculation A.

(3)

Subject to paragraph (4), where calculation B is greater than calculation A for an obligation period, the total obligation for that period is calculation B.

(4)

Where calculation B is greater than calculations A and C for an obligation period, the total obligation for that period is calculation C.

(5)

References to the total obligation in Article 12 shall be construed accordingly.

(6)

Determining the number of renewables obligation certificates to be produced by a designated electricity supplier in order to discharge his renewables obligation