OpenLegislation

The Town and Country Planning (Fees for Applications and Deemed Applications) (Amendment) (England) Regulations 2008

Draft. This instrument was laid in draft and may differ from the one made. Look for the made version under its title.

Draft 2008, ISBN 9780110809892

Original text. legislation.gov.uk does not revise statutory instruments, so later amendments are not shown here. Changes made to it are listed under each provision when known.

Draft Regulations laid before Parliament under section 303 of the Town and Country Planning Act 1990, for approval by resolution of each House of Parliament.

Town And Country Planning, England

Made 2008

Coming into force 6th April 2008

The Secretary of State, in exercise of the powers conferred by section 303 of the Town and Country Planning Act 1990f1, makes the following Regulations, a draft of which has been laid before and approved by each House of Parliament:

Annotations to the whole text

Footnotes

f1

1990 c.8. Section 303 was amended by section 6(6) of the Planning and Compensation Act 1991 (c.34) and by section 53 of the Planning and Compulsory Purchase Act 2004 (c.5). These powers are devolved, in relation to Wales, to the Welsh Ministers; see the National Assembly for Wales (Transfer of Functions) Order 1999 (S.I. 1999/672), article 2, Schedule 1, and paragraphs 30 to 32 of Schedule 11 to the Government of Wales Act 2006 (c.32).

Contents

  1. 1Citation, commencement and application
  2. 2Amendment of Regulations
  3. 3Revocation
  4. Signature
  5. Schedule 1: PART SUBSTITUTED FOR PART 2 OF SCHEDULE 1 TO THE 1989 REGULATIONS
  6. 2Part 2
  7. Schedule 2: SCHEDULE SUBSTITUTED FOR SCHEDULE 2 TO THE 1989 REGULATIONS
  8. EDULE 2Part EDULE 2
  9. Explanatory note

1Citation, commencement and application

(1)

These Regulations may be cited as the Town and Country Planning (Fees for Applications and Deemed Applications) (Amendment) (England) Regulations 2008 and shall come into force on 6th April 2008.

(2)

These Regulations apply in relation to England only.

2Amendment of Regulations

(1)

The Town and Country Planning (Fees for Applications and Deemed Applications) Regulations 1989f1 are amended as follows.

(2)

After regulation 1(2)(a) (application), insert —

“(aa)

to requests for confirmation that a condition or conditions attached to a grant of planning permission has been complied with where the request is made on or after 6th April 2008;”.

(3)

In regulation 10A (fees for applications for certificates of lawful use or development)—

(a)

in paragraph (5)(b), for “£135” substitute “£170”;

(b)

in paragraph (6)(a), for “£265” substitute “£335”; and

(c)

in paragraph (6)(b)—

(i)

for “£13,250” substitute “£16,565”, and

(ii)

for “£50,000” substitute “£250,000”.

(4)

In regulation 11A (fees for certain applications under the General Permitted Development Order)—

(a)

in paragraph (1)(a), for “£50” substitute “£70”; and

(b)

in paragraph (1)(b), for “£265” substitute “£335”.

(5)

After regulation 11B (fees in respect of the monitoring of mining and landfill sites), insert —

“Fee for confirmation of compliance with condition attached to planning permission: England

11D.
(1)

Where a request is made to a local planning authority for written confirmation of compliance with a condition or conditions attached to a grant of planning permission, a fee shall be paid to that authority as follows—

(a)

where the request relates to a permission for development which falls within category 6 or 7(a) of Part 2 to Schedule 1, £25 for each request;

(b)

where the request relates to a permission for development which falls within any other category of that Schedule, £85 for each request.

(2)

Any fee paid under this regulation shall be refunded if the local planning authority fails to give the written confirmation requested within a period of twelve weeks from the date on which the authority received the request.”.

(6)

In Part 1 of Schedule 1 (general provisions)—

(a)

in paragraphs 4(1) and 6(2), for “£265” substitute “£335”;

(b)

in paragraphs 7 and 7A, for “£135” substitute “£170”;

(c)

omit paragraph 7B;

(d)

in paragraph 15(2)(a), for “£265”, substitute “£335”;

(e)

in paragraph 15(2)(b)–

(i)

for “£6,625” substitute “£8,285”; and

(ii)

for “£25,000” substitute “£125,000”.

(7)

For Part 2 of Schedule 1 (scale of fees), substitute the Part set out in Schedule 1 to these Regulations.

(8)

For Schedule 2 (scale of fees for advertisement applications), substitute the Schedule set out in Schedule 2 to these Regulations.

3Revocation

The Town and Country Planning (Fees for Applications and Deemed Applications) (Amendment) (England) Regulations 2005f1 are revoked.

Signature

Signed by authority of the Secretary of State for Communities and Local Government

Name

Parliamentary Under Secretary of State

Department of Communities and Local Government

Date

2

Scale of Fees in Respect of Applications Made or Deemed to be Made on or after 6th April 2008

Category of Development

Fee Payable

I Operations

1. The erection of dwelling houses (other than

development in category 6)

(a) Where the application is for outline

planning permission and-

  (i) the site area does not exceed 2.5

  hectares, £335 for each 0.1 hectare of the

  site area;

  (ii) the site area exceeds 2.5 hectares,

  £8,285; and an additional £100 for each

  0.1 hectare in excess of 2.5 hectares,

  subject to a maximum in total of £125,000;

(b) in other cases-

  (i) where the number of dwelling houses to

  be created by the development is 50 or

  fewer, £335 for each dwelling house;

  (ii) where the number of dwelling houses

  to be created by the development exceeds

  50, £16,565; and an additional £100 for

  each dwelling house in excess of 50

  dwelling houses, subject to a maximum in

  total of £250,000.

2. The erection of buildings (other than

buildings in categories 1, 3, 4, 5 or 7).

(a) Where the application is for outline

planning permission and-

  (i) the site area does not exceed 2.5

  hectares, £335 for each 0.1 hectare of the

  site area;

  (ii) the site area exceeds 2.5 hectares,

  £8,285; and an additional £100 for each

  0.1 hectare in excess of 2.5 hectares,

  subject to a maximum in total of £125,000;

(b) in other cases-

  (i) where no floor space is to be created by

  the development, £170;

  (ii) where the area of gross floor space to

  be created by the development does not

  exceed 40 square metres, £170;

  (iii) where the area of the gross floor space

  to be created by the development exceeds

  40 square metres, but does not exceed 75

  square metres, £335;

  (iv) where the area of the gross floor space

  to be created by the development exceeds

  75 square metres, but does not exceed

  3750 square metres, £335 for each 75

  square metres of that area;

  (v) where the area of gross floor space to

  be created by the development exceeds

  3750 square metres, £16,565; and an

  additional £100 for each 75 square metres

  in excess of 3750 square metres, subject to

  a maximum in total of £250,000.

3. The erection, on land used for the purposes

of agriculture, of buildings to be used for

agricultural purposes (other than buildings in

category 4).

(a) Where the application is for outline

planning permission and-

  (i) the site area does not exceed 2.5

  hectares, £335 for each 0.1 hectare of the

  site area;

  (ii) the site area exceeds 2.5 hectares,

  £8,285; and an additional £100 for each

  additional 0.1 hectare in excess of 2.5

  hectares, subject to a maximum in total of

  £125,000;

(b) in other cases-

  (i) where the area of gross floor space to

  be created by the development does not

  exceed 465 square metres, £70;

  (ii) where the area of gross floor space to

  be created by the development exceeds

  465 square metres but does not exceed 540

  square metres, £335;

  (iii) where the area of the gross floor space

  to be created by the development exceeds

  540 square metres but does not exceed

  4215 square metres, £335 for the first 540

  square metres, and an additional £335 for

  each 75 square metres in excess of 540

  square metres; and

  (iv) where the area of gross floor space to

  be created by the development exceeds

  4215 square metres, £16,565; and an

  additional £100 for each 75 square metres

  in excess of 4215 square metres, subject to

  a maximum in total of £250,000.

4. The erection of glasshouses on land used for

the purposes of agriculture

(a) Where the area of gross floor space to be

created by the development does not exceed

465 square metres, £70;

(b) where the area of gross floor space to be

created by the development exceeds 465 square

metres, £1,870.

5. The erection, alteration or replacement of

plant or machinery

(a) Where the site area does not exceed 5

hectares, £335 for each 0.1 hectare of the site

area;

(b) where the site area exceeds 5 hectares,

£16,565; and an additional £100 for each 0.1

hectare in excess of 5 hectares, subject to a

maximum in total of £250,000.

6. The enlargement, improvement or other

alteration of existing dwelling houses

(a) Where the application relates to one

dwelling house, £150;

(b) where the application relates to 2 or more

dwelling houses, £295.

7(a) The carrying out of operations (including

the erection of a building) within the curtilage

of an existing dwelling house, for purposes

ancillary to the enjoyment of the dwelling

house as such, or the erection or construction of

gates, fences, walls or other means of enclosure

along a boundary of the curtilage of an existing

dwelling house

£150

(b) The construction of car parks, service roads

and other means of access on land used for the

purposes of a single undertaking, where the

development is required for a purpose

incidental to the existing use of the land

£170

8. The carrying out of any operations connected

with exploratory drilling for oil or natural gas

(a) Where the site area does not exceed 7.5

hectares, £335 for each 0.1 hectare of the site

area;

(b) where the site area exceeds 7.5 hectares,

£25,000, and an additional £100 for each 0.1

hectare in excess of 7.5 hectares, subject to a

maximum in total of £250,000.

9. The carrying out of any operations not

coming within any of the above categories.

(a) In the case of operations for the winning and

working of minerals –

  (i) where the site area does not exceed 15

  hectares, £170 for each 0.1 hectare of the

  site area;

  (ii) where the site area exceeds 15

  hectares, £25,315; and an additional £100

  for each 0.1 hectare in excess of 15

  hectares, subject to a maximum in total of

  £65,000;

(b) in any other case, £170 for each 0.1

hectare of the site area, subject to a maximum

of £250,000.

II Uses of Land

10. The change of use of a building to use as

one or more separate dwelling houses.

(a) Where the change of use is from a previous

use as a single dwelling house to use as two or

more single dwelling houses-

  (i) where the change of use is to use as 50

  or fewer dwelling houses, £335 for each

  additional dwelling house;

  (ii) where the change of use is to use as

  more than 50 dwelling houses £16,565,

  and an additional £100 for each dwelling

  house in excess of 50 dwelling houses,

  subject to a maximum in total of £250,000;

(b) in all other cases-

  (i) where the change of use is to use as 50

  or fewer dwelling houses, £335 for each

  dwelling house;

  (ii) where the change of use is to use as

  more than 50 dwelling houses £16,565,

  and an additional £100 for each dwelling

  house in excess of 50 dwelling houses,

  subject to a maximum in total of £250,000.

11(a) The use of land for the disposal of refuse

or waste materials or for the deposit of material

remaining after minerals have been extracted

from land;

(b) the use of land for the storage of minerals in

the open.

(a) Where the site area does not exceed 15

hectares, £170 for each 0.1 hectare of the site

area;

(b) where the site area exceeds 15 hectares,

£25,315; and an additional £100 for each 0.1

hectare in excess of 15 hectares, subject to a

maximum in total of £65,000.

12. The making of a material change in the use

of a building or land (other than a material

change of use in category 10, 11(a) or 11(b))

£335

EDULE 2

Scale of Fees in Respect of Applications for Consent to Display Advertisements Made on or after 6th April 2008

Category of Development

Fee Payable

1. Advertisements displayed externally on

business premises, the forecourt of business

premises or other land within the curtilage of

business premises, wholly with reference to all

or any of the following matters-

(a) the nature of the business or other activity

carried on on the premises;

(b) the goods sold or the services provided on

the premises; or

(c) the name and qualifications of the person

carrying on such business or activity or

supplying such goods or services.

£95

2. Advertisements for the purpose of directing

members of the public to, or otherwise drawing

attention to the existence of, business premises

which are in the same locality as the site on

which the advertisement is to be displayed but

which are not visible from that site.

£95
3. All other advertisements.£335

Explanatory note

(This note is not part of the Regulations)

These Regulations amend the Town and Country Planning (Fees for Applications and Deemed Applications) Regulations 1989 (‘the 1989 Regulations’). The 1989 Regulations make provision for the payment of fees to local planning authorities in respect of applications made under the Town and Country Planning Act 1990 for planning permission for development or for approval of matters reserved by an outline planning permission, in respect of fees for applications for certificates of lawful use or development, in respect of applications for consent for the display of advertisements and in respect of certain applications made under the Town and Country Planning (General Permitted Development) Order 1995; and for the payment of fees to the Secretary of State in respect of applications for planning permission which are deemed to have been made in connection with an appeal against an enforcement notice.

These Regulations amend the 1989 Regulations to increase certain fees payable under those Regulations. The increase in fees is approximately 25%, though with two exceptions. In respect of applications in fee categories 6 and 7(a) (relating to the alteration of existing dwelling houses or development within the curtilage), the increase is 11%. In respect of maximum fees payable by virtue of regulation 2, the increase is to a level of £250,000 for all applications (or £125,000 for an outline application), other than applications for minerals or waste development in fee categories 9(a) and 11, where the new maximum is £65,000.

Regulation 2 also amends the 1989 Regulations to add a new category of fee where a local planning authority confirms in writing, following a request, that a condition or conditions attached to an earlier grant of planning permission have been complied with.

Replacement scales of fees (Part 2 of Schedule 1 and Schedule 2 to the 1989 Regulations) are set out in the Schedules to these Regulations.

These Regulations revoke the Town and Country Planning (Fees for Applications and Deemed Applications) (Amendment) (England) Regulations 2005 (S.I.2005/843), which made changes to the level of fees in the 1989 Regulations.

An Impact Assessment has been prepared in relation to these Regulations. It has been placed in the library of each House of Parliament and can also be viewed on the website of the Department for Communities and Local Government, www.communities.gov.uk.