Paragraph 19 Decommissioning traffic management plan

Original text. Later amendments are not shown.

(1)

Within 12 months of the date that the undertaker decides to decommission any part of the authorised development, the undertaker must submit to the relevant planning authority for its approval, after consultation with National Highways and the highway authority, a decommissioning traffic management plan for that part.

(2)

No decommissioning works must be carried out until the relevant planning authority has approved the plan submitted under sub-paragraph (1) in relation to such works.

(3)

The plan submitted and approved must include details of—

(a)

route diversions; and

(b)

routing of abnormal loads and HGVs.

(4)

The measures set out in the plan submitted under paragraph (1) must be consistent with the principles informing the measures that are set out in the register of environmental actions and commitments.

(5)

The plan must be implemented and maintained as approved for the duration of the decommissioning of the authorised development.