Introductory text
Infrastructure Planning
Made 24th September 2021
Coming into force 25th September 2021
An application has been made, under paragraph 2 of Schedule 6 to the Planning Act 2008f1 (“the 2008 Act”), to the Secretary of State in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011f2 (“the 2011 Regulations”), for a non-material change to the East Anglia ONE Offshore Wind Farm Order 2014f3 (“the 2014 Order”).
The Secretary of State, having considered the application, the responses to the publicity and consultation required by regulations 6 and 7 of the 2011 Regulations, has decided to make this Order amending the 2014 Order.
Accordingly, the Secretary of State, in exercise of the powers in paragraph 2(1) and (9) of Schedule 6 to the Planning Act 2008, makes the following Order:
Annotations
Footnotes
- f1
-
2008 c. 29. Paragraph 2 was amended by paragraph 4 of Schedule 8 to the Marine and Coastal Access Act 2009 (c. 23), by paragraphs 1 and 72 of Schedule 13 to the Localism Act 2011 (c. 20), and by section 28 of the Infrastructure Act 2015 (c. 7). There are other amendments to the Act that are not relevant to this Order.
- f2
-
S.I. 2011/2055, as amended by S.I. 2012/635, S.I. 2013/522, S.I. 2015/760 and S.I. 2020/1534. There are other amendments to the Order that are not relevant to this Order.
- f3
-
S.I. 2014/1599 as amended by S.I. 2016/447.