Paragraph 27 TrafficI1
England, Wales and Scotland
No stage of the connection works may commence until for that stage the following have been submitted to and approved by the F1relevant planning authority in consultation with the relevant highway authority—
a traffic management plan which must be in accordance with the outline traffic management plan;
a travel plan which must be in accordance with the outline travel plan; and
an access management plan which must be in accordance with the outline access management plan.
The plans approved under paragraph (1) must be implemented upon commencement of the relevant stage of the connection works.