OpenLegislation

Paragraph 7 I1

England, Wales and Scotland

(1)

In relation to an offshore electrical station, each gravity base foundation must not have a footprint at the seabed which is more than 8,011 m2.

(2)

In relation to an offshore electrical station, each jacket foundation must not have—

(a)

a footprint at the seabed which is more than F1... 15,855 m2;

(b)

 F2more than four piles per leg or more than one suction caisson per leg;

F3(c)

more than six legs.

Annotations

Textual amendments

F1

Word in Sch. 1 Pt. 3 para. 7(2)(a) omitted (16.4.2021) by virtue of The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021 (S.I. 2021/471), arts. 1, 6(j)

F2

Words in Sch. 1 Pt. 3 para. 7(2)(b) substituted (16.4.2021) by The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021 (S.I. 2021/471), arts. 1, 6(k)

F3

Sch. 1 Pt. 3 para. 7(2)(c) inserted (16.4.2021) by The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021 (S.I. 2021/471), arts. 1, 6(l)

Commencement

I1

Sch. 1 Pt. 3 para. 7 in force at 29.8.2017, see art. 1