Paragraph 12 Coordination with East Anglia ONE Offshore Wind FarmI1

England, Wales and Scotland

(1)

Prior to submission of each of the pre-construction plans and documentation required to be submitted under condition 6(1)(a) to (j) above the undertaker must provide a copy of the relevant plans and documentation to the undertaker of the offshore element of the East Anglia ONE Offshore Wind Farm to enable that undertaker to provide any comments on the plans and documentation.

(2)

The undertaker must participate in liaison meetings with the undertaker of the offshore element of the East Anglia ONE Offshore Wind Farm as requested from time to time by the MMO in writing in advance, which meeting will be chaired by the MMO and may consider such matters as are determined by the MMO relating to the efficient operation of the offshore element of the authorised project and the offshore element of the East Anglia ONE Offshore Wind Farm.

Annotations

Commencement

I1

Sch. 14 para. 12 in force at 29.8.2017, see art. 1