Article 19 Time limit for exercise of authority to acquire land compulsorilyI1

England, Wales and Scotland

(1)

After the end of the period of seven years beginning on the day on which this Order is made—

(a)

no notice to treat is to be served under Part 1 (which makes provision for compulsory purchase under the Acquisition of Land Act 1981) of the 1965 Act; and

(b)

no declaration is to be executed under section 4 (execution of declaration) of the 1981 Actf1 as applied by article 22 (application of the F1... 1981 Act).

(2)

The authority conferred by article 26 (temporary use of land for carrying out the authorised project) ceases at the end of the period referred to in paragraph (1), except that nothing in this paragraph prevents the undertaker remaining in possession of land after the end of that period, if the land was entered and possession was taken before the end of that period.

Annotations

Textual amendments

F1

Words in art. 19(1)(b) omitted (22.12.2022) by virtue of The East Anglia TWO Offshore Wind Farm (Correction) Order 2022 (S.I. 2022/1399), art. 1(2), Sch.

Commencement

I1

Art. 19 in force at 22.4.2022, see art. 1(2)

Footnotes

f1

Section 4 was amended by sections 184 and 185 of, and paragraph 2 of Schedule 18 to, the Housing and Planning Act 2016 (c. 22).