OpenLegislation

Paragraph 9 Detailed offshore design parametersI1

England, Wales and Scotland

The total amount of scour protection for the wind turbine generators, construction, operation and maintenance platform, meteorological mast and offshore electrical platform forming part of the authorised project must not exceed 1,606,983 m2.

Annotations

Commencement

I1

Sch. 1 Pt. 3 para. 9 in force at 22.4.2022, see art. 1(2)