Paragraph 12 EarthworksI1

England, Wales and Scotland

No phase of the authorised development (with the exception of the highway works which are governed by requirements 4 and 5 and Schedule 19 (for the protection of Highways England) and 20 (for protection of Leicestershire County Council as highway authority)) is to commence until details of—

(a)

the earthworks strategy relating to that phase of development including the management and protection of soils;

(b)

an Earthworks Specification for each phase of the development;

(c)

cutting slopes and embankment design that would accord with the approved Earthworks Specification;

(d)

the extent of any material to be temporarily stored within the site; and

(e)

any surplus material to be removed from the site for disposal or material to be imported to the site,

have been approved in advance and in writing by the local planning authority. All earthworks must be carried out in accordance with the details as approved.