Paragraph 4 I1
England, Wales and Scotland
The undertaker must give Tarmac no less than 28 days’ notice of the commencement of any of the specified works and must include with the notice a programme of those works. Once the specified works which are the subject of the notice have commenced they must be completed without delay in accordance with the programme.
Annotations
Commencement
- I1
Sch. 21 para. 4 in force at 2.2.2016, see art. 1