Made 20th June 2018

Coming into force 22nd June 2018

An application has been made, under paragraph 2 of Schedule 6 to the Planning Act 2008(f1), to the Secretary of State in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011f2 for a non-material change to The East Northamptonshire Resource Management Facility Order 2013.

The Applicant, Aegean South Ltd, has publicised and consulted on this proposed amendment to the Order in accordance with Regulations 6 and7of the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 and has provided the Secretary of State with a Publicity and Consultation Statement in accordance with Regulation 7A of the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011.

Accordingly, the Secretary of State, in exercise of the powers conferred by paragraphs 2(1) and (9) of Schedule 6 to the Planning Act 2008, makes the following Order—

Annotations to the whole text

Footnotes

f1

2008 c. 29. Paragraph 2 was amended by paragraph 4 of Schedule 8 to the Marine and Coastal Access Act 2009 (c. 23), by paragraphs 1 and 72 of Schedule 13 to the Localism Act 2011 (c. 20), and by section 28 of the Infrastructure Act 2015(c. 7). There are other amendments to the Act that are not relevant to this Order

f2

S.I. 2011/2055, as amended by S.I. 2012/635 and S.I. 2015/760.

Contents

  1. 1Citation and commencement
  2. 2Amendments to The East Northamptonshire Resource Management Facility Order 2013
  3. 3Amendments to Schedule 1 (Authorised Project)
  4. 4Amendments to Schedule 2 (Requirements)
  5. Signature
  6. Explanatory note

1Citation and commencement

This Order may be cited as the East Northamptonshire Resource Management Facility (Amendment) Order 2018 and comes into force on 22nd June 2018.

2Amendments to The East Northamptonshire Resource Management Facility Order 2013

The East Northamptonshire Resource Management Facility Order 2013 (“the 2013 Order”) is amended as follows.

3Amendments to Schedule 1 (Authorised Project)

Schedule 1 (Authorised Project) of the 2013 Order is amended as follows—

(a)

In paragraph 1, in the section headed, “Works No.2”, for “100,000tpa” substitute “150,000tpa” and

(b)

In paragraph 1, in the section headed “Works No.2”, for “150,000tpa” substitute “200,000tpa”.

4Amendments to Schedule 2 (Requirements)

Schedule 2 (Requirements) of the 2013 Order is amended as follows –

(a)

In paragraph 10, under the heading “Quantities of waste”, for “waste that shall be imported to the soil treatment facility per annum will be 150,000 tonnes”, substitute “waste that shall be imported to the soil treatment facility per annum will be 200,000 tonnes”.

Signature

Signed by authority of the Secretary of State for Housing, Communities and Local Government

Bourne of Aberystwyth

Parliamentary Under Secretary of State

Ministry of Housing Communities and Local Government

20th June 2018

Explanatory note

(This note is not part of the Order)

This Order amends The East Northamptonshire Resource Management Facility Order 2013, a development consent order under the Planning Act 2008, following an application made in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 for a non-material change under paragraph 2 of Schedule 6 to the Planning Act 2008. This Order amends the description of the authorised project (see article 3), and one aspect of the requirements of the authorised project, namely, it expands the quantities of waste permitted to be imported to the soil treatment facility (see article 4).

A hard copy of this Order will be displayed on the site.