Paragraph 83 I1

The undertaker must give to National Grid not less than 14 days’ notice in writing of its intention to commence construction of any National Grid connection works and notice in writing of its completion not later than 7 days after the date on which it is completed and National Grid will be entitled by its officer to watch and inspect the construction of such works.

Annotations

Commencement

I1

Sch. 14 para. 83 in force at 31.5.2025, see art. 1