Paragraph 10 ArchaeologyI1

England and Wales

(1)

No part of the authorised development may commence, and no part of the permitted preliminary works for that part comprising the intrusive archaeological surveys may start, until an overarching written scheme of investigation for that part has been submitted to and approved in writing by the relevant planning authority for that part or, where the part falls within the administrative areas of East Riding of Yorkshire Council and North Yorkshire Council, both relevant planning authorities.

(2)

The written scheme of investigation must be substantially in accordance with the overarching written scheme of investigation and must be implemented as approved.

Annotations

Commencement

I1

Sch. 2 para. 10 in force at 31.5.2025, see art. 1