Paragraph 14 Operational noiseI1
England and Wales
(1)
No part of Work No. 1 or Work No. 2 may commence until an operational noise assessment containing details of how the design of the authorised development has incorporated mitigation to ensure the operational noise rating levels as set out in the environmental statement are to be complied with for that part has been submitted to and approved by the relevant planning authority for that part.
(2)
The mitigation measures described in the operational noise assessment for each part of the authorised development must be implemented as approved.
Annotations
Commencement
- I1
Sch. 2 para. 14 in force at 31.5.2025, see art. 1