OpenLegislation

Part 4 TEMPORARY MANAGEMENT OF PUBLIC RIGHTS OF WAYI1

England and Wales

(1)

Area

(2)

Public right of way

(3)

Measure (Public Right of Way to be managed during construction to maintain Public Right of Way continuity and access through the site).

East Riding of YorkshireBUBWF17Public Right of Way between points PRoW-02/01 and PRoW-03/01 as shown on Sheets 2 and 3 of the streets, rights of way and access plans to be managed during construction of the authorised development.
East Riding of YorkshireFOGGF13Public Right of Way between points PRoW-03/01 and PRoW-04/01 as shown on Sheets 3 and 4 of the streets, rights of way and access plans to be managed during construction of the authorised development.
East Riding of YorkshireSPALF16Public Right of Way between points PRoW-04/03 to PRoW-04/04 as shown on Sheet 4 of the streets, rights of way and access plans to be managed during construction of the authorised development.
East Riding of YorkshireSPALF15Public Right of Way between points PRoW-04/05 and PRoW-06/03 as shown on Sheets 4 and 6 of the streets, rights of way and access plans to be managed during construction of the authorised development.
East Riding of YorkshireFOGGF05Public Right of Way between points PRoW-05/01 and PRoW-06/01 as shown on Sheets 5 and 6 of the streets, rights of way and access plans to be managed during construction of the authorised development.
East Riding of YorkshireFOGGF05Public Right of Way between points PRoW-06/02 and PRoW-06/04 as shown on Sheet 6 of the streets, rights of way and access plans to be managed during construction of the authorised development.
East Riding of YorkshireSPALF19Public Right of Way between points PRoW-06/05 and PRoW-06/06 as shown on Sheet 6 of the streets, rights of way and access plans to be managed during construction of the authorised development.
East Riding of YorkshireSPALB08Public Right of Way between points PRoW-07/01 and PRoW-07/03 as shown on Sheet 7 of the streets, rights of way and access plans to be managed during construction of the authorised development.
East Riding of YorkshireBUBWS11Public Right of Way between points PRoW-08/01 and PRoW-08/03 as shown on Sheet 8 of the streets, rights of way and access plans to be managed during construction of the authorised development.
East Riding of YorkshireBUBWF10Public Right of Way between points PRoW-08/02 and PRoW-08/04 as shown on Sheet 8 of the streets, rights of way and access plans to be managed during construction of the authorised development.
East Riding of YorkshireSPALF17Public Right of Way between points PRoW-10/01 and PRoW-10/03 as shown on Sheet 10 of the streets, rights of way and access plans to be managed during construction of the authorised development.
East Riding of YorkshireSPALF18Public Right of Way between points PRoW-10/06 and PRoW-11/01 as shown on Sheets 10 and 11 of the streets, rights of way and access plans to be managed during construction of the authorised development.
East Riding of YorkshireEASTB17Public Right of Way between points PRoW-11/02 and PRoW-11/03 as shown on Sheet 11 of the streets, rights of way and access plans to be managed during construction of the authorised development.
East Riding of YorkshireWRESF07Public Right of Way between points PRoW-15/01 and PRoW-17/02 as shown on Sheets 15 and 17 of the streets, rights of way and access plans to be managed during construction of the authorised development.
East Riding of YorkshireWRESF06Public Right of Way between points PRoW-16/01 and PRoW-16/02 as shown on Sheet 16 of the streets, rights of way and access plans to be managed during construction of the authorised development.
East Riding of YorkshireWRESF06Public Right of Way between points PRoW-16/04 and PRoW-17/01 as shown on Sheets 16 and 17 of the streets, rights of way and access plans to be managed during construction of the authorised development.
East Riding of YorkshireWRESF10Public Right of Way between points PRoW-16/05 and PRoW-16/06 as shown on Sheet 16 of the streets, rights of way and access plans to be managed during construction of the authorised development.
East Riding of YorkshireWRESF08Public Right of Way between points PRoW-16/07 and PRoW-16/08 as shown on Sheet 16 of the streets, rights of way and access plans to be managed during construction of the authorised development.
East Riding of YorkshireWRESF09Public Right of Way between points PRoW-17/01 and PRoW-17/03 as shown on Sheet 17 of the streets, rights of way and access plans to be managed during construction of the authorised development.
North Yorkshire Council35.45/9/1Public Right of Way between points PRoW-18/01 and PRoW-18/02 as shown on Sheet 18 of the streets, rights of way and access plans to be managed during construction of the authorised development.
East Riding of YorkshireWRESF12Public Right of Way between points PRoW-18/03 and PRoW-18/04 as shown on Sheet 18 of the streets, rights of way and access plans to be managed during construction of the authorised development.
North Yorkshire Council35.45/6/1Public Right of Way between points PRoW-21/01 and PRoW-21/02 as shown on Sheet 21 of the streets, rights of way and access plans to be managed during construction of the authorised development.
North Yorkshire Council35.47/1/2Public Right of Way between points PRoW-22/01 and PRoW-22/02 as shown on Sheet 22 of the streets, rights of way and access plans to be managed during construction of the authorised development.

Annotations

Commencement

I1

Sch. 6 Pt. 4 in force at 31.5.2025, see art. 1