The Eggborough Gas Fired Generating Station Order 2018 (“the Order”)f1, which granted development consent within the meaning of the Planning Act 2008 (“the Act”)f2, contains correctable errors within the meaning of the Actf3.

In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, before the end of the relevant period, as defined in paragraph 1(6)(a) of Schedule 4 to the Act, the Secretary of State received a written request from the applicantf4 for the correction of errors in the Order.

In accordance with paragraph 1(7) of Schedule 4 to the Act, the Secretary of State has informed North Yorkshire County Council and Selby District Council, as the relevant local planning authoritiesf5, that the request has been received.

The Secretary of State, in exercise of the powers conferred by section 119 of, and paragraphs 1(4) and 1(8) of Schedule 4 to the Act, makes the following Order:

Annotations to the whole text

Footnotes

f1

S.I. 2018/1020

f2

2008 c. 29. Paragraph 1 of Schedule 4 was amended by paragraph 70 of Schedule 13, and Part 20 of Schedule 25, to the Localism Act 2011 (c.20) and by paragraph 4 of Schedule 8 to the Marine and Coastal Access Act 2009 (c.23). There are other amendments to the Act which are not relevant to this Order.

f3

As provided for in paragraph 1(3) of Schedule 4 to the Act.

f4

As defined in paragraph 4 of Schedule 4 to the Act.

f5

As defined in paragraph 4 of Schedule 4 to the Act.

Contents

  1. 1Citation and commencement
  2. 2Corrections
  3. Signature
  4. Schedule Corrections
  5. Explanatory note

1Citation and commencement

(1)

This Order may be cited as the Eggborough Gas Fired Generating Station (Correction) Order 2018.

(2)

This Order comes into force on 7th December 2018.

2Corrections

(1)

The Eggborough Gas Fired Generating Station Order 2018 is corrected as set out in the table in the Schedule to this Order, where—

(a)

column 1 sets out where the correction is to be made;

(b)

column 2 sets out how the correction is to be made; and

(c)

column 3 sets out the text which is to be substituted, inserted or omitted.

Signature

Signed by authority of the Secretary of State for Business, Energy and Industrial Strategy

Gareth Leigh

Head of Energy Infrastructure Planning

Department for Business, Energy and Industrial Strategy

6th December 2018

Corrections

Column (1)Column (2)Column (3)
Where the correction is madeHow the correction is madeText substituted, inserted or omitted
Article 6For article 6, substitute
“6.

Subject to article 7 (consent to transfer benefit of the Order), the provisions of this Order have effect solely for the benefit of Eggborough Power Limited save for—

(a)

Work No. 3B, in relation to which this Order has effect for the benefit of Eggborough Power Limited and NGET; and

(b)

Work No. 7A, in relation to which this Order has effect for the benefit of Eggborough Power Limited and NGG.”

Article 7(1)(b)For “by”, substitute“between”
Article 11(12)For “(Protective Provisions for the Protection of the Canal and River Trust)”, substitute“(for the protection of Canal and River Trust)”

Explanatory note

(This note is not part of the Order)