Paragraph 21 Construction workers travel plan

(1)

No part of the authorised development may commence, save for the permitted preliminary works, until a construction workers travel plan has been submitted to and, after consultation with the highway authority, approved by the relevant planning authority.

(2)

The plan submitted and approved must be in accordance with chapter 14 of the environmental statement and the framework construction workers travel plan contained in appendix 14A of the environmental statement.

(3)

The plan submitted and approved must include—

(a)

measures to promote the use of sustainable transport modes to and from the authorised development by construction staff;

(b)

provision as to the responsibility for, and timescales of, the implementation of those measures;

(c)

details of parking for construction personnel within the construction sites; and

(d)

a monitoring and review regime.

(4)

The approved plan must be implemented within three months of commencement of the authorised development and must be maintained throughout the construction of the authorised development unless otherwise agreed with the relevant planning authority.