OpenLegislation

Paragraph 4 Notice of commencement of commercial use and requirement for cessation of existing coal-fired power station electricity generation

(1)

Notice of the intended start of commercial use of the authorised development must be given to the relevant planning authority where practicable prior to such start and in any event within seven days from the date that commercial use is started.

(2)

The authorised development must not enter commercial use if the existing coal-fired power station has not ceased to generate electricity.