Paragraph 7 Public rights of way diversions
No part of the authorised development may commence, save for the permitted preliminary works, until a public rights of way management plan for any sections of public rights of way shown to be temporarily closed on the access and rights of way plans for that part has been submitted to and, after consultation with the highway authority, approved by the relevant planning authority.
The plan must include details of—
measures to minimise the length of any sections of public rights of way to be temporarily closed; and
advance publicity and signage in respect of any sections of public rights of way to be temporarily closed.
The plan must be implemented as approved unless otherwise agreed with the relevant planning authority in consultation with the highway authority.